1. General
1.1 Various situations may occur to a
Knowledge Transfer Partnership during its lifetime. The more challenging issues to be resolved
can include the Associate leaving early and the company partner withdrawing.
1.2 The Grant Offer Letter (GOL) requires the
Partnership to take action immediately when an event occurs which will, or is
likely to, result in progress towards completion of the Partnership ceasing or
being delayed, for example the resignation of a KTP Associate. The Knowledge
Base Partner is required to notify Innovate UK without delay, about the
occurrence of the event and the action, if any; it proposes to take in order
that progress is resumed.
1.3 When notifying delays in progress and
preparing the case for action, the Partnership need to bear in mind the aims of
KTP in delivering benefits to all three parties – a company, a knowledge base
organisation and a graduate. The guiding
principal should therefore be to take actions that maximise these aims.
1.4 Before the Local Management
Committee (LMC) decides on which course of action to undertake early
discussions with your nominated KTP Adviser is essential. The KTP Adviser must
agree to endorse any such actions and will take in to account the following LMC
Guidance.
1.5 We continue to see a significant
delay in the time taken for the Partnership to come to a decision and to then
make the online revision request when there is a need to replace an Associate
or Finish Off. This is inconsistent with one of the main aims of KTP to provide
a timely strategic solution for the business partner. Innovate UK therefore expects
to receive a revision request on the Portal within two months of the associate
leaving and the revised end date (the last date the Associate is deemed to be
working on the project). Please make
sure the operations team are notified of any changes as soon as possible. This
must be done during the notice period or before they have actually left as this
enables us to ensure, when appropriate, that automated email requests for the
Final Report are sent in good time.
Taking action sooner rather than later can help to avoid disappointment
as late requests to replace the Associate or finish off are unlikely to be
supported.
1.6 It is unlikely that Innovate UK will
agree for an Associate to be replaced more than once. The replacement Associate must have started
work on the project within 9 months of the revision request being agreed by the
Innovate UK.
1.7 You are reminded that existing
guidance on the revisions process states that if the project has a further 12
to 36 months to run a case to appoint a replacement Associate may be made. In these circumstances Innovate UK expects
the Partnership to recruit a replacement Associate and not ‘finish off’ the
project by using a member of staff from the KB.
No additional funding will be made available when replacement associates
are appointed.
2. Guidance for the LMC Requests for
additional funding and/or time extensions
2.1 The approval of any additional funding or
time extension to complete the Project(s) is exceptional. If the Local Management Committee wishes to
seek additional funding or a time extension for the original Partnership the
following should be noted.
Normally, additional funding will
only be considered in cases where an Associate has resigned within the first
2 or 3 months of an Associateship.
- No application will be considered
within three months of the end of a Partnership.
- Additional Government funding
will not be provided to enable Associates to complete their Projects after
the end of their contracts. It is
expected that any funding for this will be provided totally by Company
Partners.
- Confirmation that the company is
prepared to contribute to its share of the costs involved is required
before a revision request is commenced.
A letter from the company is required and should be attached to the
application made via the Portal.
- Any additional grant funding
awarded should be complemented by additional funding from the Company
Partner in a proportion at least as large as the proportion of company
funding contribution provided to the original budget.
- If an Associate leaves towards
the end of his Associateship, the partners may apply to ‘finish off’ the
Partnership, whereby another person can be employed to do the work but
he/she is not classed as an Associate.
- Someone appointed to ‘finish off’
is expected to already have the necessary skills needed to pick up the
project and get started without any delay and they are not permitted to
expend funds from the Associate Development Eligible Costs. Innovate UK is unlikely to extend the
end date of the project set for the last Associate.
2.2 In practice there are three approaches to
consider:
Approach
1 - Closure
The Partnership closes.
Approach
2 - Replacement
A case is made
for a replacement Associate to be appointed and for the Partnership to run for
a further 12-36 months
Approach
3 – Finishing Off
A case is made
for use of some of the remaining
funds to realise a large part of the Partnership objectives, and at least
secure benefits to two out of the three parties.
(This might be
for example by employing a research assistant to complete the work or by
releasing more academic time. Without an
Associate present, this approach is less satisfactory than Approach 2 in some
respects, but it may deliver the hoped for benefits to the two remaining
parties and maybe some benefits to a research assistant)
Where an
Associate leaves at a key point during the implementation phase near the end of
the project a revision request can be made to ‘finish off’. Under these circumstances the person
appointed to finish off is not deemed to be the Associate, and cannot make use of the Associate
Development budget. The rules on virement and what can be expended
from each budget headings remains unchanged. In particular moving funding
into or out of Employment Costs is not permitted. Someone appointed to ‘finish
off’ is expected to already have the necessary skills needed to pick up the
project and get started without any delay.
Innovate UK is unlikely to agree to extend the end date beyond the date
set for the last Associate.
The case should
state what work is to be done and the benefits, what funding is required,
normally from within the existing budget, how many months it will take and who
is going to do it (note that it cannot be a company employee).
Which approach to
pursue depends upon each case and should take into account the circumstances
and the views of the company and knowledge base partners.
It should not be
seen as an opportunity to seek additional funding or extend the life of the
project and/or to undertake new work.
2.3 Possible
scenarios are:
The Associate
leaves near the end of the Partnership, with most of the objectives
realised. Approach 1 may be preferred
with perhaps just local initiatives to round things off.
An Associate
leaves during the first 2 or 3 months.
Approach 2 may be favoured.
The Associate
leaves at a key point during the implementation phase near the end of the
Partnership. Approach 3 may be
appropriate.
The company
partner withdraws. This would normally
result in the end of the Partnership, but there may be exceptional cases where
a short continuance - i.e. Approach 3 - would allow the agendas of the
knowledge base partner and the Associate to be more fully realised.
In practice,
Approaches 2 and 3 will always require the case to be made to Innovate UK using
the Online Revision via the KTP Portal and approved before work is
commenced. Advisers should of course use
their knowledge of the particular circumstances and their judgement to decide
whether either course of action is in practice desirable. Certainly Approach 3 is not intended to be a
way of “using up remaining grant money” and should be driven by the implementation
of the project.
3. Guidance for the LMC Requests for
Virement
The LMC is
permitted to make decisions about Virement without having to make a formal
request to Innovate UK and any decisions about virement must of course have the
support of the nominated KTP Adviser. No
requests for virement may be made after the end date of the last project
completion. All requests must be
supported by a justification as to why the request is being made. It is not sufficient to just state that it
was agreed by the LMC and then insert the amounts and all such requests must
have the support of the KTP Adviser.
- No Virement may be made from the
Associate Development heading.
- The decisions made by the LMC
must be formally recorded in the minutes of the meeting and a copy of the
LMC Minutes should be included as an attachment to the Revision
application made using the KTP Portal.
- Should the need to action a
Virement fall in between LMC meetings then the KTP Adviser must make this
clear in the appropriate comment box.
Please note that where this has not been agreed in the last LMC
minutes, the Knowledge Base must enter the date of the last meeting.
5. When
Academics leave
5.1 KTP grants are given to the knowledge
base, not individual academics so there is no ‘right’ for academics to take
projects with them if they leave the knowledge base before the project has
ended.
5.2 Where an academic supervisor leaves, the
knowledge base must find a suitable replacement. This search and appointment is generally
conducted by the projects lead academic supported by HR, and must comply with
any KB selections processes. The
business must be consulted regarding the appointment and agree to the
appointment of the new supervisor.
5.3 When the academic lead moves KB:
Option 1: is for the KB to offer the business a
replacement academic, and if the business accepts, the project stays with the
KB and the academic’s change.
Option 2: is that
the current KB agrees to buy the academics time from their new knowledge base,
and this gets paid for out of the existing budget.
Option 3: if the KB
cannot agree with the new KB to buy the academics time, cannot offer a
replacement academic, or if the business doesn’t think the new academic team
has the required skills, then it is possible for the project to be moved to
another institution. The current KB and
new KB must agree to the move as there are financial implications for
both. The budget stays the same which
can cause issues if overheads are higher at the new KB and if travel costs are
increased. The new KB also has to find
appropriate supervisors. The whole
project is transferred including the associate.
The programme manager requires letters from each KB and the business
agreeing to the move.